National Project:
SAFE AND HIGH-QUALITY MOTORWAYS
Geographical spread of projects:
Krasnodar Territory, Penza, Lipetsk, Ryazan Region, Tomsk Region
Project | Construction of a new high‑speed motorway to the Kerch Strait crossing |
Work done | Five 10/0.4 kV integrated cubicle transformer substations were designed and built; the 10 kV switchgear was designed and built with installation of 2 line cubicles at Raduga 110/10 kV substation, as well as 10 kV feeder PTLs with a total length of more than 6 km was built |
Outcome | Connected capacity totalled 376 kW |
Project | Reconstruction of a motorway, which is the shortest route for cargo and passenger transportation from the airport to the federal road R‑208 (Tambov – Penza), thus bypassing Penza downtown |
Work done | 10 kV OTL was built and 10 kV integrated transformer substation was installed |
Outcome | Outdoor lighting of the motorway with a total capacity of 38 kW was connected |
Project | Renovation of the motorway along 50 Let NLMK street in Lipetsk |
Work done | Two 10 kV cable lines were rearranged (789 m were laid). Six 110 kV cable lines were rearranged to protect the existing 110 kV cable line (600 m), routing of 16‑fibre FOCL (1,118 m) and 8‑fibre FOCL (2,213 m) |
Outcome | Land plot was cleared off of PJSC Rosseti Centre power grid facilities |
Project | Heavy resurfacing of the Taradei – Kuliki – Fedosovo motorway in the Shatskiy district of the Ryazan region |
Work done | 0.4 kV OTL (228 m long) was rearranged; 10 kV OTL (67 m) was rearranged; 14 towers were dismantled and re‑installed |
Outcome | The motorway complies with regulatory requirements |
Project | Construction of motorway Knyazevo – Topily in Skopinsky and Miloslavsky districts of the Ryazan Region |
Work done | Works on rearrangement of electrical grids, dismantling and installation of towers were carried out |
Outcome | The motorway complies with regulatory requirements |
Project | Construction of an automatic in‑motion weight and size check station at 273 km of the Tomsk – Kargala – Kolpashevo motorway in the Kolpashevsky district of the Tomsk Region |
Work done | Grid connection with 10 kW maximum power of consumer terminals was made |
Outcome | New traffic light systems, as well as automatic weight and dimensional check systems were installed |