Key operational risks realised in 2023
Realised risk | Indicator | Risk realisation in the reporting period (amount of actual deviation of the risk‑underlying indicator from the planned (target) value) | Reasons for risk realisation | |
---|---|---|---|---|
% | abs. | |||
KOR‑003 Risk of deviation of the grid connection scope from the target value set in the business plan | Execution of grid connection agreements | −42% | −1,934 MW | In 2023, it was planned to execute 135 agreements for a total maximum capacity of 4,571 MW. In fact, 179 agreements were executed, with the maximum capacity amounting to 2,637 MW. Decrease in the volume of connected maximum capacity by 1,934 MW is due to rescheduling of certificate singing under grid connection agreements for the following reasons: 1. Unpreparedness of applicants, including:
2. Absence of grid connection fees established by the FAS of Russia, including:
3. Rescheduling of certificate singing under agreement No. 286/TP‑M6 dated 18.11.2019 with JSC Vyksa Metallurgical Plant, 240 MW in accordance with Additional Agreement No. 2 dated 13.09.2023 (grid connection of GPP-10) |
Revenue from grid connection services | + 55% | + RUB 10,223 mln | ||
Number of executed agreements, signed grid connection certificates | + 33% | + 44 pcs. |