National Project:
DEMOGRAPHY

Geographical spread of projects:

St. Petersburg, Republic of Mordovia, Belgorod, Kaluga Region, Nizhny Novgorod Region

PJSC Rosseti Lenenergo

Project Multifunctional sports centre in St. Petersburg
Work done For reliable power supply to the facility, the Company’s specialists routed 0.4 kV cable lines and installed a power metering system
Outcome 500 kW of power was provided. The power supply source is Zavod Libknekhta 110 kV substation

PJSC Rosseti Volga

Project Construction of the Zarechny Residential Centre for the Elderly and Disabled in the Republic of Mordovia
Work done Construction of 10 kV OTL with protected wire (3.64 km), 10 kV cable line (0.64 km) was completed; 10/0.38 kV double‑transformer integrated transformer substation (1,000 kVA installed capacity of each transformer) was installed, and 0.38 kV cable line (0.2 km) was built
Outcome The facility was connected to the grid

PJSC Rosseti Centre

Project Construction of the Siren (Lilac) Centre for Rhythmic Gymnastics, Trampolining and Sports Acrobatics in Belgorod
Work done Power supply grids, including 14 cable lines (0.4 kV) with total length of 2,045 m, 12 cable lines (6 kV) with total length of 2,326 m, were rearranged; TP‑48 transformer substation was dismantled/reinstalled
Outcome The sports centre is up and running, and expected to host major regional competitions

PJSC Rosseti Centre and Volga Region

Project Aquatoria Sports and Fitness Centre in Balabanov, Kaluga Region
Work done Grid connection was completed. Connected capacity is 0.32 MVA. PTL length is 0.52 km
Outcome The first municipal swimming pool was built in the Borovsky district of the Kaluga Region. The new sports complex has two pools (10 m and 25 m); water access for low‑mobility visitors is provided

PJSC Rosseti Centre and Volga Region

Project Novoslobodsky Residential Centre for the Elderly and Disabled in the Duminichsky district of the Kaluga Region
Work done Grid connection was completed. The volume of connected capacity is 0.5 MVA. PTL length is 1.1 km
Outcome The capacity of the institution was expanded and living conditions for the elderly and disabled were improved

PJSC Rosseti Centre and Volga Region

Project Construction of an indoor football arena at the Borsky sports complex in the Nizhny Novgorod Region
Work done Grid connection completed. Connected capacity is 1.26 MVA. PTL length is 1.66 km