The Rosseti Group has an extensive investment programme.
The goals of the Rosseti Group’s investment programme are as follows:
To develop main and interregional power grids as part of the electric power complex of the Russian Federation
To ensure reliable and uninterrupted transmission of electric power to consumers
To ensure functioning of the wholesale market
To facilitate joint operation of the Russian electric power system and electric power systems of foreign countries
To ensure the economically sustainable and profitable operation of the Rosseti Group
To improve the quality and reliability of electricity supply for end consumers
To maintain tariff‑based sources of investment in grid renewal and expansion
To grow the Company, while creating of added value both in the electric power industry and in new markets
To bolster interaction with consumers, the Rosseti Group and investors
Main areas of the investment programme
Renewal of equipment required for sufficient, reliable and uninterrupted power supply to consumers
Introduction of new capacities if necessary to cover load deficits or create a capacity margin
Reduction of production costs, in part by improving equipment efficiency, using more cost‑effective technical solutions and reducing losses
Higher safety of equipment operation, including environmental safety
Upgrade and renewal of fixed assets
Provision for grid connections
Consolidation of power grid assets
Rosseti Group’s investment programme is reviewed annually to align it with industry development plans and customer needs.
The investment programme is financed primarily from the Rosseti Group’s own funds. The share of borrowed funds in the investment programme budgeting is 14%.
The indicators are on the downward trend, which is explained by the absence of approved long‑term investment programmes for some subsidiaries of the Rosseti Group, including PJSC Rosseti, in the period from 2026 to 2028.
Rosseti Group’s consolidated investment programme for 2024–2028 (approved in 2023)
Financing, RUB mln (VAT included)
Indicator
2024
2025
2026
2027
2028
2024–2028
Distribution complexIncluding interdependent companies.
264,418
244,700
188,153
185,887
28,643
911,800
Transmission complex
325,907
1,032
1,030
0
0
327,969
Total for the Rosseti Group
590,325
245,732
189,183
185,887
28,643
1,239,769
Commissioning of fixed assets, RUB mln (VAT excluded)
Distribution complexIncluding interdependent companies.
299,013
238,058
163,371
173,666
22,086
896,194
Transmission complex
338,976
696
1,018
0
0
340,690
Total for the Rosseti Group
637,988
238,754
164,389
173,666
22,086
1,236,884
Commissioning of PTLs as fixed assets, km
Distribution complexIncluding interdependent companies.
23,753
18,754
15,046
16,196
3,203
76,951
Transmission complex
1,983
0
0
0
0
1,983
Total for the Rosseti Group
25,736
18,754
15,046
16,196
3,203
78,934
Commissioning of transformer capacity as fixed assets, MVA
Distribution complexIncluding interdependent companies.
7,143
5,145
4,327
3,296
276
20,187
Transmission complex
11,263
0
0
0
0
11,263
Total for the Rosseti Group
18,406
5,145
4,327
3,296
276
31,450
Implementation of Rosseti Group’s investment programme in 2023
In 2023, the Rosseti Group implemented a record‑setting investment programme, covering the power supply to new transport, industrial and social facilities, and residential complexes, including those built under national projects in accordance with the Decree of the President of the Russian Federation, Vladimir PutinPresidential Decree No. 204 dated 7 May 2018 «On National Goals and Strategic Objectives for the Development of the Russian Federation until 2024»..
In the reporting year, the Rosseti Group managed to meet the investment programme targets, while maintaining the planned level of financing. Commissioning of fixed assets in value terms exceeded the target by 17%, commissioning of transformer capacity — by 18%, and commissioning of PTLs — by 24%.
Key performance parameters of the Rosseti Group’s consolidated investment programme in 2023
330 kV OTL from Kursk NPP – Sumy Severnaya 330 kV OTL to Belgorod 330 kV substation
542 km
Construction of Centralnaya – RP‑9 20 kV, DC high‑temperature superconducting cable line
2.5 km
Grid connection JSC Obukhov Plant (MIC)
Troitskaya 110 kV substation with 110 kV PTL
160 MVA
8 km
Grid connection of a data centre PJSC Sberbank
Chapaevskaya 220 kV substation with 220 kV OTL
200 MVA
26 km
Construction of power grid facilities in the Southern Federal District
Novaya 220 kV substation with 110–220 kV PTL
125 MVA
26 km
Reliability improvement programmes in the North Caucasian Federal District
Renovation of 17 facilities in the Republic of Dagestan
Renovation of 4 facilities in the Chechen Republic
445 MVA
17 km
Reliability and grid connection facilities for large consumers in the Tyumen Region
Moskovskaya 110 kV substation with 110 kV OTL
Shakurovskaya 110 kV substation with 110 kV OTL
Renovation of Snezhnaya – Khanty Mansiyskaya 110 kV OTL
160 MVA
160 km
Objects of the Integrated Development Plan of the Republic of Tyva
Turan – Tumannaya 220 kV OTL
Renovation of Oznachennoye 500 kV substation
Renovation of Kyzylskaya 220 kV substation
1,131 MVA
272 km
Grid connection of CJSC Nakhodka Fertiliser Plant
Renovation of Lozovaya – Nakhodka 220 kV aerial cable line
67 km
Grid connection of LLC RENERA‑Enertek
Zavodskaya 110 kV with 110 kV OTL
126 MVA
7 km
Implementation of PJSC Rosseti’s Investment Programme
PJSC Rosseti’s investment programme is aligned with opinions of key stakeholders, including consumers, federal and regional authorities, and relevant ministries and agencies, as well as strategic objectives for developing grid infrastructure and strengthening the national energy security.
Thus, the programme for 2023–2024 incorporated the comments and proposals received during the public discussion of the draft document in March 2023, initiatives of federal executive authorities, constituent entities of the Russian FederationIn accordance with the procedure defined by Resolution of the Government of the Russian Federation No. 977 dated 1 December 2009., as well as decisions of the Minenergo of Russia.
The document includes measures to improve energy security of the Russian Federation, increase the capacity of controlled cross‑sections between the Interconnected Power System (ICPS) of the Urals and the ICPS of Siberia, increase the efficiency of interconnection capacity utilisation, and ensure the possibility of additional transmission of electric power and capacity from the ICPS of the Urals to the ICPS of Siberia in low‑water years.
PJSC Rosseti’s investment programme also takes into account grid connection projects, as well as new interconnection measures for parallel synchronous operation of the ICPS of Siberia and the ICPS of the East. This will make it possible to launch a competitive market pricing mechanism for electricity and capacity in the eastern regions and improve the reliability and quality of power supply to consumers.
The total amount of investments planned for 2023–2024 is RUB 583.6 billion. Implementation of PJSC Rosseti’s investment programme will address the main crucial tasks of maintaining the technical condition of the UNPG, including the nationwide tasks of ensuring the operation of critical facilities, including socially important ones.