Investment activities

Rosseti Group’s Investment Programme for 2024–2028 approved in 2023:
  • Financing of the Investment Programme — RUB 1,239.8 bln, VAT included
  • Commissioning of fixed assets — RUB 1,236.9 bln, VAT excluded
  • Commissioning of transformer capacity — 31.5 GVA
  • Commissioning of power transmission lines — 78,900 km

The Rosseti Group has an extensive investment programme.

The goals of the Rosseti Group’s investment programme are as follows:

  • To develop main and interregional power grids as part of the electric power complex of the Russian Federation
  • To ensure reliable and uninterrupted transmission of electric power to consumers
  • To ensure functioning of the wholesale market
  • To facilitate joint operation of the Russian electric power system and electric power systems of foreign countries
  • To ensure the economically sustainable and profitable operation of the Rosseti Group
  • To improve the quality and reliability of electricity supply for end consumers
  • To maintain tariff‑based sources of investment in grid renewal and expansion
  • To grow the Company, while creating of added value both in the electric power industry and in new markets
  • To bolster interaction with consumers, the Rosseti Group and investors
Main areas of the investment programme
Renewal of equipment required for sufficient, reliable and uninterrupted power supply to consumers Introduction of new capacities if necessary to cover load deficits or create a capacity margin
Reduction of production costs, in part by improving equipment efficiency, using more cost‑effective technical solutions and reducing losses Higher safety of equipment operation, including environmental safety
Upgrade and renewal of fixed assets Provision for grid connections
Consolidation of power grid assets

Rosseti Group’s investment programme is reviewed annually to align it with industry development plans and customer needs.

The investment programme is financed primarily from the Rosseti Group’s own funds. The share of borrowed funds in the investment programme budgeting is 14%.

Power line support
Budgeting of the Rosseti Group’s investment programme, RUB bln (VAT included)
Commissioning by Rosseti Group, RUB bln (VAT excluded)
Rosseti Group’s commissioning volumes

The indicators are on the downward trend, which is explained by the absence of approved long‑term investment programmes for some subsidiaries of the Rosseti Group, including PJSC Rosseti, in the period from 2026 to 2028.

Electrical substation
Rosseti Group’s consolidated investment programme for 2024–2028 (approved in 2023)
Financing, RUB mln (VAT included)
Indicator 2024 2025 2026 2027 2028 2024–2028
Distribution complexIncluding interdependent companies. 264,418 244,700 188,153 185,887 28,643 911,800
Transmission complex 325,907 1,032 1,030 0 0 327,969
Total for the Rosseti Group 590,325 245,732 189,183 185,887 28,643 1,239,769
Commissioning of fixed assets, RUB mln (VAT excluded)
Distribution complexIncluding interdependent companies. 299,013 238,058 163,371 173,666 22,086 896,194
Transmission complex 338,976 696 1,018 0 0 340,690
Total for the Rosseti Group 637,988 238,754 164,389 173,666 22,086 1,236,884
Commissioning of PTLs as fixed assets, km
Distribution complexIncluding interdependent companies. 23,753 18,754 15,046 16,196 3,203 76,951
Transmission complex 1,983 0 0 0 0 1,983
Total for the Rosseti Group 25,736 18,754 15,046 16,196 3,203 78,934
Commissioning of transformer capacity as fixed assets, MVA
Distribution complexIncluding interdependent companies. 7,143 5,145 4,327 3,296 276 20,187
Transmission complex 11,263 0 0 0 0 11,263
Total for the Rosseti Group 18,406 5,145 4,327 3,296 276 31,450
Alexey Molsky
— Will there be any changes to project financing given the tasks currently facing the united Company?

— Grid infrastructure is one of the basic systems that influence the national energy security and lay the groundwork for social and economic growth. The Rosseti Group is now dealing with ambitious tasks associated with the electrification of the Eastern Railway Range and higher reliability of power supply to consumers, including in the North Caucasus, as well as other fundamental issues.

Along with this, every year we see an increasing imbalance between target and system financing. Tariff sources along are not enough to fulfil of all existing tasks, and therefore the investment mechanisms need to be revised.

Though there are federal budget funds allocated, which are planned for reliability improvement programmes, however, electrification of the Eastern Range and debottlenecking are system projects that are implemented upon targeted business requests. For these projects, we suggest financing mechanisms that are similar to capacity delivery agreements (CDA) in the generation sector. Another option is to use funds from the positive unbalance of the Nodal Price Difference Fund (NPDF).

Alexey Molsky, Deputy General Director for Investments and Capital Construction

Implementation of Rosseti Group’s investment programme in 2023

In 2023, the Rosseti Group implemented a record‑setting investment programme, covering the power supply to new transport, industrial and social facilities, and residential complexes, including those built under national projects in accordance with the Decree of the President of the Russian Federation, Vladimir PutinPresidential Decree No. 204 dated 7 May 2018 «On National Goals and Strategic Objectives for the Development of the Russian Federation until 2024»..

In the reporting year, the Rosseti Group managed to meet the investment programme targets, while maintaining the planned level of financing. Commissioning of fixed assets in value terms exceeded the target by 17%, commissioning of transformer capacity — by 18%, and commissioning of PTLs — by 24%.

Sources of financing for the investment programme in 2023, %
Key performance parameters of the Rosseti Group’s consolidated investment programme in 2023
S&A/SoS Financing, RUB mln, VAT included Commissioning, RUB mln, VAT excluded Commissioning, km Commissioning, MVA
Distribution complex
PJSC Rosseti Siberia 13,518 8,811 1,802 336
PJSC TDC 954 587 111 24
JSC Rosseti Tyumen 16,182 8,477 311 144
PJSC Rosseti Ural 20,239 14,446 7,605 1,652
PJSC Rosseti Volga 9,862 8,968 1,448 127
PJSC Rosseti South 5,417 3,523 681 115
PJSC Rosseti Kuban 18,235 11,960 1,052 606
PJSC Rosseti Northen Caucasus 4,502 3,246 288 67
JSC Chechenenergo 3,975 758 324 14
PJSC Rosseti Centre and Volga Region 31,484 24,919 7,515 1,122
PJSC Rosseti North‑West 8,841 7,678 1,830 223
PJSC Rossetti Lenenergo 46,823 36,946 2,467 907
JSC Rosseti Yantar 4,116 3,665 375 67
PJSC Rosseti Centre 20,666 18,443 3,366 451
PJSC Rosseti Moscow Region 71,664 72,715 5,480 1,737
PJSC Rosseti Siberia Tyvaenergo 527 440 187 28
JSC RES 5,554 4,292 490 390
JSC EESK (Ekaterinburg Power Grid Company) 3,090 1,925 352 206
JSC TGES 553 446 53 14
JSC VMES 374 385 128 21
Total for the distribution complex 286,577 232,631 35,865 8,251
Transmission complex
PJSC Rosseti 248,808 111,787 909 1,594
JSC Electromagistral 1,512 806 0.7 63
Total for the transmission complex 250,320 112,593 909 1,657
Total for the Rosseti Group 536,897 345,224 36,774 9,908
Key investment projects in 2023
BAM and Trans‑Siberian Railway facilities:
  • Nizhneangarskaya – Ust‑Kut 500 kV OTL with Nizhneangarskaya 500 kV substation
  • Zilovo – Kholbon 220 kV OTL, Zilovo – Mogocha 220 kV OTL
  • Ust‑Ilimskaya HPP – Ust‑Kut No. 3 500 kV OTL
  • Komsomolskaya – Start No. 1 220 kV OTL
1,002 MVA
1,171 km
Retrofitting of Dmitrov 220 kV substation and Raduga 220 kV OTL
  • Yartsevo (grid connection of JSC Special Economic Zone of Technology and Innovation Dubna)
18.6 km
Comprehensive renovation of Zavod Ilyich 330 kV substation
376 MVA
Renovation of 110 kV power supply centres in the Sochi energy district
  • Renovation of Pasechnaya 110 kV substation
  • Renovation of Adler 110 kV substation
  • Renovation of Kudepsta 110 kV substation
210 MVA
Renovation of Raduga 500 kV substation (grid connection of JSC Vyksa Metallurgical Plant)
250 MVA
Grid connection of oil and gas facilities in Khanty‑Mansi Autonomous District — Yugra
  • Renovation of Tavricheskaya – KNS‑5 110 kV OTL
  • Sorovskaya 2 110/35/6 kV substation with 110 kV OTL
80 MVA
31 km
Grid connection of industrial facilities of the Siberian Federal District
  • Ust‑Kut – Kovykta 220 kV OTL
  • Renovation of NPS‑7 – NPS‑9 220 kV OTL
  • Ozernaya 220 kV substation and Chita – Ozernaya 220 kV OTL
  • Renovation of Taiga 220 kV substation – Razdolinskaya 220 kV substation, Priangarskaya – Razdolinskaya 220 kV OTL
876 MVA
761 km
Grid connection of industrial facilities of the Far Eastern Federal District
  • Nyuya 220 kV substation and Nyuya – Chayanda 220 kV OTL
  • Khimkombinat 500 kV substation with renovation of Zeyskaya HPP – Amurskaya 500 kV OTL
  • Nergen 500 kV substation
126 MVA
101 km
Renovation of 6–10 kV distribution grids in Kaliningrad
  • Upgrade of 300 transformer substations/power distribution substations
14 km
Key investment projects in 2024
BAM and Trans‑Siberian Railway facilities
  • Nizhneangarskaya – Taksimo 500 kV OTL
  • Nizhneangarskaya – Ust‑Kut No. 2 500 kV OTL
  • Agorta – Dauria 500 kV OTL with Dauria 500 kV substation and Agorta 500 kV substation
1,002 MVA
1,000 km
Comprehensive Infrastructure Modernisation and Development Plan (RF Government Order No. 2101‑r dated 30.09.2018)
  • Makkaveevo – Chita 220 kV OTL
  • Prizeyskaya – Elgaugol 220 kV OTL with Elgaugol 220 kV substation
  • 330 kV OTL from Kursk NPP – Sumy Severnaya 330 kV OTL to Belgorod 330 kV substation
542 km
Construction of Centralnaya – RP‑9 20 kV, DC high‑temperature superconducting cable line
2.5 km
Grid connection JSC Obukhov Plant (MIC)
  • Troitskaya 110 kV substation with 110 kV PTL
160 MVA
8 km
Grid connection of a data centre PJSC Sberbank
  • Chapaevskaya 220 kV substation with 220 kV OTL
200 MVA
26 km
Construction of power grid facilities in the Southern Federal District
  • Novaya 220 kV substation with 110–220 kV PTL
125 MVA
26 km
Reliability improvement programmes in the North Caucasian Federal District
  • Renovation of 17 facilities in the Republic of Dagestan
  • Renovation of 4 facilities in the Chechen Republic
445 MVA
17 km
Reliability and grid connection facilities for large consumers in the Tyumen Region
  • Moskovskaya 110 kV substation with 110 kV OTL
  • Shakurovskaya 110 kV substation with 110 kV OTL
  • Renovation of Snezhnaya – Khanty Mansiyskaya 110 kV OTL
160 MVA
160 km
Objects of the Integrated Development Plan of the Republic of Tyva
  • Turan – Tumannaya 220 kV OTL
  • Renovation of Oznachennoye 500 kV substation
  • Renovation of Kyzylskaya 220 kV substation
1,131 MVA
272 km
Grid connection of CJSC Nakhodka Fertiliser Plant
  • Renovation of Lozovaya – Nakhodka 220 kV aerial cable line
67 km
Grid connection of LLC RENERA‑Enertek
  • Zavodskaya 110 kV with 110 kV OTL
126 MVA
7 km

Implementation of PJSC Rosseti’s Investment Programme

PJSC Rosseti’s investment programme is aligned with opinions of key stakeholders, including consumers, federal and regional authorities, and relevant ministries and agencies, as well as strategic objectives for developing grid infrastructure and strengthening the national energy security.

Thus, the programme for 2023–2024 incorporated the comments and proposals received during the public discussion of the draft document in March 2023, initiatives of federal executive authorities, constituent entities of the Russian FederationIn accordance with the procedure defined by Resolution of the Government of the Russian Federation No. 977 dated 1 December 2009., as well as decisions of the Minenergo of Russia.

The document includes measures to improve energy security of the Russian Federation, increase the capacity of controlled cross‑sections between the Interconnected Power System (ICPS) of the Urals and the ICPS of Siberia, increase the efficiency of interconnection capacity utilisation, and ensure the possibility of additional transmission of electric power and capacity from the ICPS of the Urals to the ICPS of Siberia in low‑water years.

PJSC Rosseti’s investment programme also takes into account grid connection projects, as well as new interconnection measures for parallel synchronous operation of the ICPS of Siberia and the ICPS of the East. This will make it possible to launch a competitive market pricing mechanism for electricity and capacity in the eastern regions and improve the reliability and quality of power supply to consumers.

The total amount of investments planned for 2023–2024 is RUB 583.6 billion. Implementation of PJSC Rosseti’s investment programme will address the main crucial tasks of maintaining the technical condition of the UNPG, including the nationwide tasks of ensuring the operation of critical facilities, including socially important ones.

According to its investment programme, the Company plans to commission 11.1 GVA of capacity and 2,000 km of power transmission lines as part of the fixed assets in 2024.
Dynamic pattern of capacity commissioning
Volume of capital investment utilisation (VAT excluded), RUB bln
Amount of financing, RUB bln
Commissioning of grid capacity as part of fixed assets, RUB bln